Thursday, October 31, 2013

Attention!! Anderson Barrel (arch) Closures to change Monday

Hi Boaters

See the notice below about upcoming changes to the arch closures at Anderson bridge. FYI, barrels=arches to many of us.

Please be aware that the changes are not instantaneous. Meaning there will be equipment and barges at large as things are getting moved around. This will require your increased situational awareness in the vicinity of the bridge. Simplified, this means look closely where you are going and what is moving toward you. 

Also be aware that construction timelines are subject to change. Due to the uncertain nature of rehab work it is always possible that there will be a delay. 

As more information becomes available Ill forward it.

Be Safe,
Aleks

---------- Forwarded message ----------
From: Boundy, Stephanie (DOT)

MassDOT's contractor plans on switching barrels in the river on Monday, November 4, 2013 and will close the center barrel closed for approximately 3 days.

They will then  switch again on Thursday, November 7, 2013,  to have the middle barrel and the Boston barrel open and the Cambridge side barrel closed.  If you need any additional information, please do not hesitate to reach out to me.

Thanks for getting the word out!

Best,


-Stephanie

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Stephanie E. Boundy| Government & Community Affairs| MassDOT






No comments:

Post a Comment